Pre-Mobilisation Checklist: What to Confirm Before Your Next Bowen Basin Shutdown

Aug 3
2 min read

Updated: Oct 3

A short one. These are the items worth confirming in writing before a crew mobilises - the ones that, left open, turn into lost hours inside the window.


Scope

  • Every access item located and listed, with the access method decided

  • Conditional items flagged, with the repair path agreed in advance

  • Confined space, hot work and overhead exposure identified


Contractor

  • IRATA membership confirmed, and the level mix named for each crew

  • Trade qualifications confirmed for the work itself, not only the access

  • Insurance certificates of currency sighted

  • Inductions complete for every named person


Documentation

  • Scope-specific SWMS accepted, not a generic template

  • Site-specific risk assessment

  • Rescue plan naming who performs the rescue

  • Equipment inspection records current


Inspection

  • NDT methods specified and the inspector's certification confirmed against them

  • Reporting format and turnaround agreed, so findings land in time to act on


Frequently asked questions

When should pre-mobilisation checks be complete?

Documentation and inductions at least two weeks out. Crew names and arrival times at least one week out. Anything confirmed in the final days tends to be confirmed twice.

The maintenance planner or shutdown coordinator, with the contractor's supervisor confirming each item back in writing. Verbal confirmation is where items go missing.

Expect that it will. The check that protects you is whether the crew on site can absorb a change - a dual-qualified crew can pick up an unplanned repair, a single-discipline crew has to remobilise.


 
 
 